Purpose
The Factory Acceptance Test (FAT) is part of the Phaesun quality process to check all the equipment which is included in the solar system before shipment.
Content
- Listing of equipment
- Test of the equipment (regulation unit, array junction boxes, converters and/or inverters)
- Review of the logistics aspects (type of packing, marking)
- Conclusion and report of test (factory commissioning)
Standard Process
Day 1:
- Premises visit
- Introduction to security aspects
- Review of the reference documents
- Electrical test on the regulation unit
Day 2:
- Counting and visual check of the equipment
- Logistics points review
- FAT closure